Tasks — Roadmap view
The Roadmap view shows only tasks tagged Milestone, across in-progress projects. It is the company-level counterpart of the Gantt (every task) and the Workload (who is doing what).
Switch between two readings of the same data:
| Layout | What it answers |
|---|---|
| Projects | Where each engagement stands. One row per project, diamond markers on a shared time axis, a vertical line for today |
| Month | When milestones land. A calendar; each chip is a milestone on its due date |
What you can do
- Open a milestone — Click a diamond or a calendar chip to open the task
- Move in time — Use ‹ › or Today. Projects shows four months from the selected month; Month shows that calendar month
- Filter — The project filter and search box on the Tasks page still apply (search matches project name)
Overdue unfinished milestones use the destructive color. Done milestones are muted. Private milestones you cannot see stay unlabeled and are not clickable.
tip
Use the Roadmap to scan the company. Use the Gantt view to plan individual tasks, and the Workload view to set who works on what next.